1909 - SAP 009-608-037 CR 8 Over Stoney Brook, Replace culverts with Bridge 09J40 and 60" PC-CS Pipe Culverts and approach gradingLandwehr Construction, Inc. KGM CONTRACTORS INC NORTHLAND CONSTRUCTORS Rachel Contracting, Inc A Plus Landscaping, LLC. KTM Paving 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$12,502.00$12,502.00$27,000.00$27,000.00$30,000.00$30,000.00$44,070.00$44,070.00$30,000.00$30,000.00$25,279.91$25,279.91
2101.501CLEARING & GRUBBINGLS1$12,550.00$12,550.00$8,000.00$8,000.00$4,000.00$4,000.00$4,400.00$4,400.00$1,000.00$1,000.00$14,718.28$14,718.28
2104.503REMOVE PIPE CULVERTSL F153$14.50$2,218.50$17.75$2,715.75$16.00$2,448.00$14.10$2,157.30$10.00$1,530.00$54.54$8,344.62
2105.504GEOTEXTILE FABRIC TYPE 6S Y710$2.00$1,420.00$3.75$2,662.50$2.20$1,562.00$2.50$1,775.00$3.00$2,130.00$3.17$2,250.70
2105.507COMMON EXCAVATION (P)C Y5,105$7.50$38,287.50$12.95$66,109.75$15.00$76,575.00$9.85$50,284.25$16.00$81,680.00$15.13$77,238.65
2105.507GRANULAR BORROW (CV) (P)C Y1,350$21.00$28,350.00$19.50$26,325.00$28.50$38,475.00$24.50$33,075.00$22.00$29,700.00$25.89$34,951.50
2105.601DEWATERINGLS1$3,610.00$3,610.00$3,800.00$3,800.00$1,150.00$1,150.00$6,400.00$6,400.00$5,000.00$5,000.00$10,150.54$10,150.54
2105.601TEMPORARY STREAM DIVERSION SYSTEMLS1$3,625.00$3,625.00$8,000.00$8,000.00$10,000.00$10,000.00$35,700.00$35,700.00$10,000.00$10,000.00$6,287.34$6,287.34
2118.507AGGREGATE SURFACING (CV) CLASS 5 (P)C Y920$32.00$29,440.00$35.45$32,614.00$35.00$32,200.00$34.60$31,832.00$35.00$32,200.00$31.53$29,007.60
2411.507STRUCTURE EXCAVATION CLASS U (P)C Y1,772$11.50$20,378.00$13.15$23,301.80$18.00$31,896.00$9.20$16,302.40$15.00$26,580.00$15.42$27,324.24
2412.50212X8 PRECAST CONCRETE BOX CULV END SECTEACH2$20,940.00$41,880.00$23,150.00$46,300.00$24,000.00$48,000.00$21,994.00$43,988.00$30,000.00$60,000.00$29,757.61$59,515.22
2412.50312X8 PRECAST CONCRETE BOX CULVERTL F78$1,050.00$81,900.00$1,165.00$90,870.00$1,150.00$89,700.00$1,097.50$85,605.00$1,300.00$101,400.00$1,431.26$111,638.28
2451.507GRANULAR BACKFILL (CV) (P)C Y1,432$21.00$30,072.00$24.50$35,084.00$21.00$30,072.00$25.70$36,802.40$22.00$31,504.00$25.54$36,573.28
2451.507COARSE AGGREGATE BEDDING (CV) (P)C Y220$34.00$7,480.00$45.00$9,900.00$34.00$7,480.00$53.80$11,836.00$35.00$7,700.00$55.56$12,223.20
2501.50360" PC-CS PIPE CULVERTL F148$240.00$35,520.00$277.00$40,996.00$415.00$61,420.00$451.00$66,748.00$350.00$51,800.00$246.15$36,430.20
2511.507RANDOM RIPRAP CLASS IIIC Y40$87.00$3,480.00$80.00$3,200.00$70.00$2,800.00$105.00$4,200.00$100.00$4,000.00$217.57$8,702.80
2511.507RANDOM RIPRAP CLASS SPECIALC Y105$85.00$8,925.00$91.00$9,555.00$64.00$6,720.00$94.35$9,906.75$100.00$10,500.00$133.99$14,068.95
2511.507HAND-PLACED RIPRAPC Y4$285.00$1,140.00$110.00$440.00$315.00$1,260.00$880.00$3,520.00$500.00$2,000.00$404.09$1,616.36
2563.601TRAFFIC CONTROL SUPERVISORLS1$950.00$950.00$1,500.00$1,500.00$500.00$500.00$50.00$50.00$500.00$500.00$3,172.04$3,172.04
2563.601TRAFFIC CONTROLLS1$5,600.00$5,600.00$6,500.00$6,500.00$4,000.00$4,000.00$5,770.00$5,770.00$4,400.00$4,400.00$9,516.13$9,516.13
2573.501EROSION CONTROL SUPERVISORLS1$1,450.00$1,450.00$2,500.00$2,500.00$500.00$500.00$50.00$50.00$100.00$100.00$3,172.04$3,172.04
2573.503SILT FENCE; TYPE HIL F2,610$3.40$8,874.00$3.10$8,091.00$3.00$7,830.00$3.35$8,743.50$2.50$6,525.00$4.31$11,249.10
2573.503SEDIMENT CONTROL LOG TYPE WOOD FIBERL F120$3.50$420.00$3.20$384.00$3.20$384.00$3.50$420.00$4.00$480.00$5.08$609.60
2574.507COMMON TOPSOIL BORROWC Y610$18.00$10,980.00$30.00$18,300.00$25.00$15,250.00$7.25$4,422.50$40.00$24,400.00$39.90$24,339.00
2575.501TURF ESTABLISHMENTLS1$1,790.00$1,790.00$1,680.00$1,680.00$1,670.00$1,670.00$1,850.00$1,850.00$1,500.00$1,500.00$2,156.99$2,156.99
2575.504EROSION CONTROL BLANKETS CATEGORY 3NS Y7,320$1.70$12,444.00$1.55$11,346.00$1.60$11,712.00$1.75$12,810.00$2.00$14,640.00$2.41$17,641.20
2575.523RAPID STABILIZATION METHOD 3MGAL0.35$725.00$253.75$685.00$239.75$680.00$238.00$750.00$262.50$5,000.00$1,750.00$862.80$301.98
 Totals for project 1909 $405,539.75 $487,414.55 $517,842.00 $522,980.60 $543,019.00 $588,479.75
 
Contract Total:$405,539.75$487,414.55$517,842.00$522,980.60$543,019.00$588,479.75